Things are moving quickly in the Reviving Your Wetlands restoration of San Elijo Lagoon. Today, you are seeing the beginning of three debris control booms.
Image Above: This debris control boom for Reviving Your Wetlands lagoon restoration will ensure that cord grass and other vegetation from the project clearing process stays in the lagoon and cannot reach the beach. The pipes are in place to maintain water flow through the railroad construction zone as Build NCC constructs the new track and bridge.
Map: Shows areas of activity in January 2018 for the Reviving Your Wetlands—San Elijo Lagoon Restoration
The construction of the dredge launch pad is set to begin. This will include vegetation removal, the construction of a ramp from the North County Transit District (NCTD) railroad (via Harbaugh Seaside Trails) to the dredge pad. The Ross Island Dredge No. 10 (see below) will be transported to the dredge launch pad in pieces and assembled onsite. The Ross Island Dredge No. 10 will be the main piece of equipment removing the sand from the dredge pit.
Image Above: When fully assembled, this is how the dredge will look.
Length (including Ladder) 120′ | Breadth: 30’ | Depth: 5’
Vegetation clearing will continue in the Central Basin and begin in the East Basin.
Thank you for following Lagoon Connections (click follow on the home page in lower right corner). As continuing schedules and insights occur during Reviving Your Wetlands—San Elijo Lagoon Restoration—your Southern California nonprofit land trust is keeping you informed. Share your questions with us!